Project Name: Rack Number/ID: Location: Date:
Checklist Items
No. Item Checked Remarks
1 Rack physical condition (no damage/defects)
2 Rack doors (front/rear) open/close and lock properly
3 Cable management accessories installed
4 Proper labeling (rack ID, power, network, etc.)
5 Power outlet(s) working and available
6 Grounding cable installed
7 Blanks/cover panels in place
8 Environmental sensors (if required) present
9 Asset tag applied (if applicable)
10 Other (specify)
Notes
Handover By (Name & Signature):
Date:
Received By (Name & Signature):
Date: