Generator Installation and Commissioning Checklist

Project Details
Project Name
Site Location
Date
Generator Model
Serial Number
Installed By
Site Preparation
Item Checked Remarks
Site cleared and levelled
Foundation/check pad leveled
Vibration pads installed
Access for maintenance ensured
Mechanical Installation
Item Checked Remarks
Generator placed correctly
Bolt torque checked
Exhaust system installed
Cooling system connected
Electrical Installation
Item Checked Remarks
Main cables connected
Earthing done
Control panel wired
Installations comply with standards
Fuel System
Item Checked Remarks
Fuel tank installed and connected
Pipes and hoses leak-free
Ventilation adequate
Fuel level checked
Pre-Commissioning Checks
Item Checked Remarks
Oil level checked
Coolant level checked
Battery connections
All safety devices tested
Manual rotation (if applicable)
Commissioning
Item Checked Remarks
Initial start-up performed
Voltage and frequency verified
No abnormal noise/vibration
Load tested
Automatic transfer switch tested